HomeMy WebLinkAbout01.09.96 Planning Packet
- .
.
.
.
;I ,
AGENDA
PLANNING COMMISSION
REGULAR
JANUARY 9, 1996
7:00 P.M.
1. CALL TO ORDER
2. APPROVE MINUTES
a. December 12, 1995 - Regular
3. PUBLIC HEARINGS
a. 7:00 P.M. - Dakota County Estates 9th Addition - Density
Increase - Continued from December 12th
b. 7:15 P.M. - Consider TroyHill PUD
c. 7:30 P.M. - Discuss 68 Child Daycare Center at Townsedge Mall
4. DISCUSSION
a. Temporary Sign Request from Sienna Corporation for East Farmington
5. ADJOURN
.
.
.
.
~
AGENDA REPORT
PLANNING COMMISSION
REGULAR MEETING
JANUARY 9, 1996
l.
CALL TO ORDER
2.
APPROVE MINUTES
3.
PUBLIC HEARINGS
a.
7:00 P.M. - Continued Hearing - Dakota County Estates 9th Addition
Density Increase Requested by Tim Giles
The concept of four quad buildings to replace three quads that were proposed as part
of the Dakota County Estates PUD has been changed to two 8 unit buildings that each
contain two handicapped accessible facilities. The proposal is similar to the
Wensmann Townhouse development situated immediately to the north and, as such, will
provide more usable open space for residents than the previously submitted four
building plan.
The plan responds to engineering questions raised earlier by including a loop road
through the site which includes ample room for utilities. The south building should
be moved five feet closer to English Avenue to provide more space separating it from
the adjoining lot to the east. In addition, the planting plan should be augmented by
adding shrub plantings to the grass panels which provide entrances to the dwelling
units. The applicant has not submitted building elevations. If they arrive before
the report is mailed, they will be sent without comment.
Recommendation
Forward the site plan to the City Council with a recommendation to approve the
density increase requested from l2 housing units to l6 on this site, subject to
moving one building and adding foundation plantings.
b. 7:15 P.M. - Consider TroyHi1l POD - 133 lots in the NE 1/4 of Section 23,
immediately north of TroyHill
TroyHill PUD is an extension of the TroyHill plat which was approved in the Spring of
1994. It is double the size of the original and is expected to retain the character
of that development. A review of the requirements of Planned Unit Developments
suggests that this neighborhood will reflect positively on the City of Farmington.
The PUD is consistent with the Farmington Comprehensive Plan, it is under unified
control, and will harmonize with development on adjoining sites.
The land area being developed includes 55.4 acres and will be built at 2.4 units per
acre. All uses are to be single family dwellings with the exception of Lot 74 near
the southern limits of the project which will be made available to the City for a
public water system well. Two outlots will be used for stormwater treatment and
stormwater storage. The eastern outlot is also available for extending the City
trail system. The southern end is recommended to be widened to 20 feet to allow
space on either side of the path. It is also recommended that the trail be installed
with the second addition. A neighborhood park has not been proposed because the
..
.
Comprehensive Park Plan indicates a large community park on the adjoining property to
the west which is an extension of the City's stormwater drainage system. The site is
a regraded gravel pit which includes enough level land to provide a moderate sized
athletic field.
The developer has asked for no increase in density and will maintain front yard
setbacks substantially larger than the City code allows. While the Developer has not
calculated building coverage and the smallest lots average lO,200 square feet, there
should not be a problem maintaining the required 20% building coverage over the
entire PUD area. However, the PUD should include setbacks of 20 feet adjoining all
lot lines which form the perimeter of the PUD. This could be accomplished with the
addition of a note to the typical lot standards on the schematic site plan. The
assumption has been made that housing styles will be similar to the housing currently
being built within Phase l. However the final plan booklet will need to include some
typical housing elevations and floor plans that will be built within the PUD.
The staging plan is relatively straight forward and includes two phases which are
anticipated to be filled by the year 2000. This may be a conservative estimate,
based upon the limited lot potential within existing MUSA limits.
The PUD requirements indicate that modifications in street standards are possible.
Because the plans do not indicate any typical street cross sections, it is assumed
that the streets will follow the current standard of 34 feet back to back.
.
The City Engineer has recommended moving the well site from Lot 74 to Lot 50 which
includes more latitude in locating the actual well. He has also recommended a
reconfiguration of Outlot B in order to accommodate the transition in elevation
between the two north/south streets on either side of the outlot. The Developer is
working with the Engineer on a grading plan that is intended to satisfy these
concerns.
An additional concern has been raised about phasing because of the need to get the
sanitary trunk sewer to the north end of the property. This could be achieved by
building the north end of Everest Path and adding Lots 62,63,ll2,l23,l24,l25, and l26
to the first phase or by providing the City a sanitary sewer easement until the 3rd
addition is implemented.
While it is not a PUD issue, the Engineer has also pointed out that 190th Street is
currently not on the Municipal State Aid (MSA) system, and it will need to be built
at some time during the development of both TroyHil1 and Nelsen Hills Farm. The
Developer responsibility for this road will be worked out within the development
agreements for the plats as they are built. The same is true for an l8 inch water
main which will be installed within the 190th Street right of way, however, the City
will participate in the cost of the water main.
One final comment is that Everest Path will need to be a direct cross intersection
with 190th Street. Whichever plat is developed first will establish the actual
location of this street intersection. The utility plans for the PUD will be analyzed
in detail when the plats are submitted for approval.
Reconunendation
.
Approve the PUD of TroyHill subject to the City Engineer's satisfaction that grading
for a stormwater pond can be accommodated within Outlot B.
Ir
. c.
7:30 P.M. - Discuss a 68 Child Daycare Facility as Requested by Kristi Ordoff
Located in the North End of Townsedge Mall.
A daycare of this size requires a conditional use permit within the B-l Limited
Business District. The applicant plans to enclose a play space with a chain link
fence and place 6 inches of sand under a play structure. As indicated in the
returned public hearing notice from one neighbor, this does not appear to be much
separation from vehicular traffic and., during summer months, the asphalt play surface
is likely to be very hot. The staff would encourage the Commission to consider the
addition of plant materials that would address these concerns. The facility layout
appears to be quite efficient and the floor plan will be available during the
meeting.
One concern about the center is that one sign was approved for the billiard parlor in
1992 and Paster Enterprises, the former building owner, was asked to prepare a plan
for signs as indicated in the code. This was not done and several temporary signs
have been installed without permit while the center was owned by Paster. The new
owner has indicated that he is interested in developing a sign plan but has not yet
been in to discuss it. The applicant for the daycare business said that a sign has
been ordered. A sign permit will not be issued by staff until some agreement is
reached on signs for the whole building. The applicant needs to be made aware of
this circumstance.
Recommendation
.
Approve the conditional use subject to the preparation and implementation of a sign
plan for all businesses in the center and preparation of a planting plan that will
better define the play area or separate it from the parking lot.
4. DISCUSSION
Sienna Corporation is requesting to erect a temporary sign promoting Park Place on
either Outlot I or J of East Farmington First Addition. When the East Farmington PUD
was approved, the plan indicated that neighborhood signs would be placed at the
entrance similar to the one that was erected in Akin Park Estates. By the time that
East Farmington was platted, the site of the proposed signs were designated as
outlots which were dedicated to the City for street purposes. Normally, signs are
not permitted within public rights of way, however, since the signs are part of the
approved PUD the City is obligated to recognize the assumed prior approval.
Recommendation
Approve the temporary promotional sign for either Outlot I or J as requested.
~~~-~
Charles Tooker
City Planner
.